§ 3.14.00. Required improvements—Monuments.
(a)
Iron pipes. Iron pipes shall be placed at all block corners, angle points and points of curves in streets required by the director of public works.
(b)
Permanent reference markers. Permanent reference monuments shall meet all the specifications set out in F.S. § 177.091.
(c)
Location; construction. The location of all permanent reference monuments shall be indicated on the final plat. All iron pipes and pins and permanent reference monuments shall comply with F.S. § 177.031.
(d)
Lot corners. Lot corners shall be monumented with iron pipes, iron pins or permanent reference monuments.
(e)
Time of placement. Permanent reference monuments (P.R.M.) and permanent control points (P.C.P.) shall be set in accordance with F.S. § 177.091, except all monuments including lot corners must be placed before the developer and surety are released from the developer's personal bond and the letter of credit is released, if a personal bond secured by a letter of credit has been posted. If no surety bond or personal bond secured by a letter of credit is posted, monuments must be placed prior to town acceptance for ownership and maintenance or release of the balance of the cash deposit, if the cash deposit has been made. Any and all land monuments disturbed or destroyed during construction shall be accurately witnessed and replaced at the developer's expense upon the completion of construction. The town manager or his designee may accept a certification from the developer's surveyor that the requirements of this section 3.14.00 have been satisfied.
(f)
Water/sewer line markers. Water and sewer laterals shall be marked with small painted lines on the nearest curb with paints of differing colors.